Project Description

To begin this project we performed abatement on asbestos containing floor tile and mastic as well as drywall that had asbestos containing mastic in the joints. Once the abatement was complete we performed the remainder of any demolition as seen in the drawings attached. Once demolition was complete we began our new work that is seen in the attached drawings.

SanDow’s Role

Prime Contractor

Dollar Value of Contract/Final Construction Cost

$397,055.00

Performance Timeliness

August 1, 2022 - April 21, 2023