Interior Demolition & Hazardous Materials Abatement

Federal Reserve Board

Mercury Vapor Remediation
(Rubber Gym Floor removal)

Location(s)

2051 Constitution Ave NW and 1951 Constitution Ave NW, Washington, DC

Project Description

We were required to build protective barriers in various locations throughout the buildings to protect the historical value of certain interior areas. Sandow was also required to provide Leed recycling services for both buildings. We also provided extensive interior demolition services including walls, flooring, ceilings, escalators, elevators, mechanical systems as well as hazardous material abatement for asbestos PCBs, contaminated oil, mercury containing light tubes for both buildings named above.

SanDow’s Role

Provided Project Management, Supervisors and work crews to the Federal Reserve Board, working in both buildings

Dollar Value of Contract/Final Construction Cost

$4,038,475

Performance Timeliness

March 2022 - August 2022

Project Photo Gallery