Data Room & Office Renovation
Carderock Olney
Location
Carderock Olney
Project Description
- To begin this project, we performed abatement on asbestos-containing floor tile and mastic as well as drywall that had asbestos-containing mastic in the joints.
- Once the abatement was complete, we performed the remainder of any demolition, as seen in the drawings attached.
- Once demolition was complete, we began our new work that is seen in the attached drawings.
SanDow’s Role
Prime Contractor
Dollar Value of Contract/Final Construction Cost
$397,055.00
Performance Timeliness
August 1, 2022 – April 21, 2023