5th Floor Lead Stabilization

Government Publishing Office

Location

Government Publishing Office DC

Project Description

  • We performed work during normal business hours.
  • We occupied the area on the 5th floor between A522 and A526 for the entire duration of the project.
  • We prepared the work area by placing 2 layers of 6-mil poly on the floor and a 1 layer of 6-mil poly wall around the area of work to contain it from adjacent areas that government employees were still occupying.
  • We installed a 1-stage decontamination facility that consisted of a dirty room for ingress and egress.
  • We installed negative air machines in the area to scrub the air of any lead particles.
  • We removed the loose and peeling paint from the ceiling and walls in the area using the wet scraping method. The scrapers were attached to a HEPA vacuum so that most of the paint chips were picked up by the HEPA vacuum. The chips that fell to the poly-covered floor were picked up and stored along with the contents of the HEPA vacuums in DOT-17H drums for disposal.
  • After we removed the loose and peeling paint, we encapsulated the scraped areas.

SanDow’s Role

Prime Abatement Contractor

Dollar Value of Contract/Final Construction Cost

$22,406.65

Performance Timeliness

April 11, 2023 – April 30, 2023

Exposed ceiling showcasing visible pipes and wiresExposed ceiling displaying pipes and wiresView of a ceiling featuring hanging pipes and wiresCeiling with exposed pipes and wires hanging downClean white wall and ceiling